The short answer: a full bathroom renovation takes 2 to 4 weeks on site for a standard bathroom, once demolition starts. A basic refresh can be done in under two weeks, while a large or structurally complex renovation can stretch to 6 weeks or more.
The longer answer is that the on-site time is only half the story. The homeowners who end up frustrated are almost always the ones who were never told about the planning, ordering and waterproofing stages that sit around the build itself. As QBCC-licensed builders delivering bathroom renovations across Brisbane, Logan, Ipswich and the Gold Coast, we run this timeline every week. Here is exactly how it plays out.
The Quick Answer by Renovation Type
Renovation type
Time on site
Typical total (incl. planning & ordering)
Cosmetic refresh (fixtures, paint, shower screen)
1 to 2 weeks
3 to 4 weeks
Standard full renovation
2 to 4 weeks
6 to 9 weeks
Large or structural renovation
4 to 6+ weeks
10 to 14 weeks
Before the Sledgehammer: 2 to 5 Weeks of Preparation
Design and quoting (1 to 2 weeks)
This is where layout decisions get locked in. Keeping the toilet, shower and vanity in their existing positions saves both time and money. Moving plumbing adds cost and usually a few extra days on site.
Selections and ordering (1 to 3 weeks)
Tiles, vanities, tapware, shower screens. Most items are available quickly, but custom vanities and imported tiles can have 3 to 6 week lead times. A good builder will not start demolition until everything critical is on hand or confirmed. Starting a job before the materials are ready is the number one cause of bathrooms sitting gutted for weeks.
The Week-by-Week On-Site Timeline
Week 1: Demolition and rough-in
Days 1 to 2: Strip-out. Old tiles, fixtures and (if needed) wall sheeting come out. Floors and drains are inspected. This is when surprises like water damage or termite activity show up, more on that below.
Days 3 to 5: Plumbing and electrical rough-in. Pipes and wiring are moved or replaced while the walls are open. New wall sheeting goes on.
Week 2: Waterproofing and tiling
Days 6 to 7: Waterproofing. In Queensland this must be done by a licensed applicator and comply with AS 3740. Here is the part nobody can rush: waterproofing membranes need cure time, typically 24 hours between coats and before tiling. Any builder promising to waterproof and tile on the same day is cutting a corner you will pay for later.
Days 8 to 12: Floor and wall tiling, then grouting. Tiling is usually the longest single stage, and intricate patterns or large-format tiles add time.
Week 3: Fit-off and finishing
Days 13 to 15: Vanity, toilet, tapware, shower screen and accessories are installed. Electrical fit-off: lights, exhaust fan, heated towel rail.
Days 16 to 18: Painting, silicone, final plumbing connections, cleaning and handover walkthrough.
Add a week of buffer for larger bathrooms, and you have the honest 2-to-4-week answer.
What Makes a Renovation Take Longer?
Hidden water damage. Older homes in suburbs like Woodridge, Ipswich’s character precincts and original Gold Coast beach houses often hide rotted framing or damaged substrates behind the old tiles. Allow for it in the budget and the schedule.
Moving plumbing. Relocating a toilet or shower means new drainage, sometimes cutting the slab. Add 2 to 5 days.
Material delays. Custom and imported items are the usual culprits. Order before demolition, not after.
Structural changes. Removing walls, enlarging windows or converting a bath to a walk-in shower adds trade coordination time.
Trade scheduling gaps. A renovation involves five or more licensed trades. Builders who run dedicated teams keep the handoffs tight; ad-hoc subcontracting is where “3 weeks” quietly becomes 7.
Larger, high-spec renovations like this Bridgeman Downs bathroom sit at the 4-to-6-week end of the range.
Can You Live at Home During the Renovation?
Yes, most of our clients do. If it is your only bathroom, plan for the wet-area downtime, roughly weeks 1 and 2, when there is no working shower or toilet in that room. Options include a temporary toilet hire, using an ensuite or laundry, or timing the work around a holiday.
How to Keep Your Renovation on Schedule
Finalise every selection before demolition day. Changed your mind on tiles mid-job? That is an automatic 1 to 2 week delay.
Use one licensed builder to run the whole job rather than coordinating trades yourself. In Queensland, renovation work over $3,300 must be done by a QBCC licence holder anyway.
Respect the waterproofing cure times. The fast bathroom is the one done right the first time.
Ask for a written schedule. We give every client a stage-by-stage program before work starts, so you know which days the water is off and when the tiler is coming.
Frequently Asked Questions
Can a bathroom be renovated in a week?
A cosmetic refresh, yes. A full strip-out renovation, no, not properly. Waterproofing cure times alone make a one-week full renovation impossible to do compliantly.
How long does a small bathroom or ensuite take?
Usually at the faster end: 2 to 3 weeks on site. Small rooms have less tiling but the same number of trades and the same waterproofing requirements.
How long before you can shower in a new bathroom?
Typically 24 to 48 hours after silicone and grout are finished. We confirm this at handover.
Does a bathroom renovation need council approval in QLD?
Like-for-like renovations generally do not. Structural changes or work affecting the building’s footprint can. Your builder should handle this assessment as part of the quote.
Planning Your Renovation Timeline?
We renovate bathrooms across Brisbane, Logan, Ipswich and the Gold Coast, with a fixed schedule and fixed price agreed before we start. Call 0485 863 485 or request a free quote and we will map out your exact timeline, including the stages most builders forget to mention.